PROJECT NEWS

Mineral Road Rail Bridge Repairs Completed Under Our Tarmac Maintenance Contract

An 18-week package of corrosion repairs and structural strengthening on a 130+ year-old rail bridge, delivered under live asset conditions for Tarmac.

All news

Under our seven-year maintenance contract with Tarmac, awarded to Clan in February 2025, we’ve completed a major package of corrosion repairs and strengthening works at Mineral Road Rail Bridge.

The 130+ year-old structure showed deterioration typical of ageing concrete and embedded steel, with moisture-driven defects accelerating corrosion risk. The works combined targeted investigation, structural repair, and long-term protection to extend service life and improve durability.

Scope of works

  • Breakout of defective concrete to sound substrate
  • Installation of new steel beams to strengthen cantilever verges
  • Concrete reinstatement to soffits and bearing interfaces
  • Removal of deteriorated cill beams and installation of protective RC collar
  • Cleansing and painting of existing structural steelwork
  • Brickwork cleaning, repointing, and infill of redundant recesses
  • Graffiti removal and application of anti-graffiti protective coatings

Works were delivered over an 18-week programme under live asset conditions, restoring structural integrity while reducing ongoing corrosion risk.