The Cunard Building
Basement Concrete Repairs & CFRP Strengthening
Survey-led basement concrete repairs, CFRP strengthening and long-term corrosion protection at a Grade II listed landmark on Liverpool’s waterfront.
Project details
- Location:
- Liverpool
- Heritage status:
- Grade II listed
- Services Delivered:
- Hand-Applied Mortar Repair; CFRP Strengthening; Anti-Carbonation Coatings; Surface-Applied Corrosion Inhibitors
- Project Status:
- Complete
Core works:
- Concrete repairs
- Rebar protection
- Carbon fibre strengthening
- Anti-carbonation coating
- Corrosion inhibition
Project Overview
Clan Contracting completed critical basement concrete repairs and structural strengthening at the Grade II listed Cunard Building on Liverpool’s waterfront. Following a detailed survey, defects were identified in basement soffits and sub-basement structural elements, including cracking, spalling, and exposed reinforcement.
The deterioration was linked to high carbonation and chloride contamination within the concrete, requiring targeted breakout, repair, and long-term protective measures, alongside structural strengthening using bonded carbon fibre reinforcement.
Scope of Structural Works
- Survey-led identification of defects to basement soffits, beams, and columns
- Breakout and removal of cracked and delaminated concrete to sound substrate
- Protection of exposed reinforcement using Sika MonoTop 610
- Concrete reinstatement using Sika MonoTop 612, with smoothing using Sika MonoTop 620
- Structural strengthening using Sika CarboDur CFRP laminates, bonded with Sikadur 30
- Corrosion inhibition using Sika Ferrogard 903+
- Anti-carbonation protection using Sikagard 550 W Elastic